English
English
Español
Français

Sign Up for Our E-News!

Join over 18,000 other roofers who get the Week in Roofing for a recap of this week's best industry posts!

Sign Up
NFBA - Sidebar Ad - Accredited Builder
CCS-OpenForBusiness-Sidebar
SOPREMA - Sidebar Ad - The Right Coatings for the Right Roofs (RLW on-demand)
Georgia-Pacific - Sidebar Ad - HD ISO
Renoworks - Side Bar Ad - 30 day free trial
Instant Roofer - Sidebar Ad - Free & Exclusive Roofing Leads
English
English
Español
Français

How to Protect Yourself During Supply Challenges

Contractors 3 ways ABC Supply
April 29, 2022 at 9:00 a.m.

By Mark Schmidt, ABC Supply.

3 ways for contractors to protect themselves from material price increases and customer sticker shock caused by supply challenges.

Contractors are busier than ever. Many contractors are even turning down work. Others are scheduling projects out long into the future. Compared with the downswing of a decade ago, this is a positive trend. Yet greatly increased demand faced with COVID-19 restrictions, logistical bottlenecks and difficulty in finding quality workers present major challenges to getting projects done on time and on budget.

This reality makes it vitally important for contractors to take a fresh look at their contracts. A few basic changes to contracts can add a layer of protection when things do not go as planned and can also help manage customer expectations. Changing contract terms to meet the current state of the industry is a win-win.

1 - Take control over the project schedule with excused delays

The saying that “time is money” is particularly true on construction projects. As a result, the project schedule is among the most important sections of any contract. Contractors who do not meet project schedules – often due to no fault of their own – can find themselves in breach of contract and with an unhappy owner. Worse, some states even have owner-friendly statutes that provide for enhanced damages against contractors who do not meet or properly document the project schedule.

With chronic shortages of factory workers and truck drivers and with production and shipping slowed down globally due to COVID-19, delays are now the rule rather than the exception.

Contractors should consider including terms in their agreement known as “force majeure” clauses, which protect the contractor if, for reasons beyond the contractor’s control, delays will occur. A typical force majeure clause would read something like this:

Delays or failure of performance caused by “any act, event, or condition that has a material adverse effect on the ability of a party to this Agreement to perform its obligations hereunder if such act, event, or condition is beyond the reasonable control of such party and is not the result of such party’s willful or negligent action or inaction and shall include, without limitation, (i) acts of God, war, public disorders, insurrection, rebellion, floods, hurricanes, earthquakes, lightning, or other natural calamities; (ii) acts or inaction of governmental or regulatory agencies or judicial bodies or changes in laws; (iii) explosions or fires; (iv) strikes or labor disturbances; (v) delays in obtaining goods or services from any subcontractor, materialman, or supplier by reason of any occurrence of any of the foregoing causes; or (v) any unforeseeable act or omission of any third party.” - Solid Waste Auth. of Cent. Ohio v. FirmGreen Fuels of Ohio, L.L.C., 2010 Ohio Misc. LEXIS 20220 (2010).

Other types of clauses can also be inserted to address delays in the contractor’s performance. First, it is a good practice to cover delays caused by the owner. Second, the agreement can excuse delays caused “by any other circumstances beyond the contractor’s control” to provide maximum flexibility in an uncertain environment.

2 - Build in flexible pricing

Prices are rapidly increasing due to demand and inflation. At the same time, delivery dates regularly get pushed back because of factory slowdowns and material shortages. The risk of substantial price hikes is high.

Contractors should consider getting in front of these issues with flexible price terms. One way to do so is to change the method of project delivery from “lump sum,” where there is a fixed price given at the outset, to “cost plus,” which passes through the actual costs to the owner with the contractor earning a fee on the total value of the work. Oftentimes, the “cost plus” contract includes a not-to-exceed price. This amount can be subject to adjustment if, for example, the contractor demonstrates that material costs exceed expectations documented in the contract or if there is a force majeure event.

Otherwise, a term that allows for adjustment of the contract price based on market fluctuations makes the most sense for all involved. The contractor can create goodwill by having a term that says if any material price goes down, then the savings would also be passed on to the customer.

3 - Be open to change orders for substitutions of products

Another way to deal with material shortages and procurement delays is to engage owners in a discussion about substitution of products. In some instances, there may be an equivalent or potentially even more desirable product that can be obtained more quickly. Any such changes should be documented by a written change order, with the appropriate price deduction or increase clearly identified.

Despite busier-than-ever schedules, revisiting and potentially revising contracts is a worthwhile effort. Your attorney can assist you with this process, and the costs you pay to your attorney will very likely be far less than the risk of not updating your agreement.  

Learn more about ABC Supply in their RoofersCoffeeShop® Directory or visit www.abcsupply.com.

Original source: ABC Supply

About Mark Schmidt

Mark Schmidt is Co-Chair of the Construction Law & Litigation practice section of Milwaukee, Wisconsin-based von Briesen & Roper, s.c. Mark advises on contract negotiation, strategic planning and dispute resolution. Learn more at vonbriesen.com.

This information is provided for educational and informational purposes only and is not intended as a substitute for obtaining accounting, tax, legal, or financial advice for a professional accountant or lawyer. Any opinions expressed are those of the author. ABC Supply makes no warranties regarding, and disclaims all responsibility for, the accuracy, legality, or content of this information. Any questions regarding the information provided should be addressed to the author.



Recommended For You


Comments

There are currently no comments here.

Leave a Reply

Commenting is only accessible to RCS users.

Have an account? Login to leave a comment!


Sign In
IB Roof - Coffee Conversations: Acquisitions - Banner - Register
English
English
Español
Français

Sign Up for Our E-News!

Join over 18,000 other roofers who get the Week in Roofing for a recap of this week's best industry posts!

Sign Up
People Make Roofing - Kyrah Coker - Oct
Progressive Materials - Sidebar - Free Samples
SRS - Sidebar Ad - SRS Para Latinos
Rapid RevOps - Get A Grip - Sidebar Ad Q4
ABC Supply - Sidebar Ad - Take Control of Your Work Day
Malco Tools - Sidebar Ad - Metal Benders